Burpengary East Wastewater Treatment Plant is located on Uhlmann Road, Burpengary. A comprehensive planning process was undertaken to ensure the project is delivered in an economically and environmentally sustainable way. The essential upgrade work will include:

  • new inlet works with enhanced odour control
  • new bioreactor
  • new clarifier
  • upgraded effluent disinfection
  • electrical and control upgrade to cater for the new infrastructure
  • upgrade the internal plant road

The project will start construction in May 2024 and is expected to be completed by late 2026, subject to weather and site conditions. All works will take place within the existing Burpengary East Wastewater Treatment Plant, located on Uhlmann Road, Burpengary East.

 

Location – Uhlmann Road, Burpengary

Commencement – May 2024

Completion – Late 2026

Contractor – Ventia

Capital investment – More than $100M

Burpengary East - Timeline

Early 2024
Construction contract award
May 2024
Construction commences
Late 2026